Wind

453 MW

AGL Energy

$850 mil

Planned

Cooranga North

QLD

-


Description:

123 turbines to be located on less than 2% of the site area of approximately 13,200 hectares of freehold agricultural land. Connected to a new Powerlink substation along the new Western Downs to Halys 275kV transmission line. Full operation targeted by the middle of the 2019 calendar year.

Major Contractors/Suppliers:

PPA: AGL EPC: GE/Catcon Turbines: GE

Updates:

  • 2017, Aug : AGL reaches financial close on sale of project to PARF
  • 2017, Jun : Development permit granted by Queensland Government for up to 115 turbines
  • 2017, Mar : Environmental impact study approved by state Co-ordinator-General
  • 2016 : Declared a Coordinated Project under the State Development and Public Works Organisation Act 1971

* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)


approximate representation only

Neil Cooke

Name : Neil Cooke

Title : Project Manager, Power Development

Phone : 1800 039 600

Email : [email protected]



* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)