Hybrid

60.5 MW

Windlab/ Eurus

$120mil

Under Construction

Kennedy

QLD

Battery


Description:

Facility to provide 60.5 MW of renewable energy at end of grid to test viability of planned second phase, ‘Big Kennedy’ of up to 1300 MW. Phase I to consist of 43 MW Wind, 18 MW Solar and 4 MW Li Ion battery storage.

Major Contractors/Suppliers:

EPC: Vestas and Quanta Services
Turbines: Vestas
Battery: Tesla
Solar cells: First Solar
Offtake: CS Energy
Debt finance: Clean Energy Finance Corporation

Updates:

  • 2019, Aug : Connected to grid and energised
  • 2019, Jun : Construction completed, waiting generation registration
  • 2018, May : Generation licence applied for
  • 2017, Dec : Construction started
  • 2017, Oct : Financial close, construction approved
  • 2017, Sep : 10-year offtake agreement signed with CS Energy
  • 2016, Jul : Development approval granted

* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)


approximate representation only

Roger Price

Name : Roger Price

Title : CEO & Managing Director

Phone : (02) 6175 4600

Email : roger.price@windlab.com



* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)