Solar PV

100 MW

Canadian Energy

-

Under Construction

Oakey

QLD

-


Description:

Solar photovoltaic project using Canadian Solar MaxPower2 CS6U panels. Developed in two stages; Oakey 1 Solar Farm (30MW) and Oakey 2 Solar Farm (70 MW). Oakey 1 connection to the grid expected in March 2018, with Oakey 2 expected to connect to the grid in October 2018. Foresight Group acquired 49% of Oakey 1 and 100% of Oakey 2 in October 2017.

Major Contractors/Suppliers:

EPC contractor: RCR Tomlinson
Engineering: Entura

Updates:

  • 2017, Oct : Foresight Group acquired 49% of Oakey 1 and 100% of Oakey 2
  • 2017, July : Application made for generation licence for stage 2
  • 2017, May : RCR Tomlinson awarded EPC contract
  • 2017, Apr : Entura appointed as Owner's Engineer
  • 2017, Feb : EPBC referral submitted to federal government
  • 2015, Apr : Development Approval granted by Toowoomba Regional Council allowing 6 years to commence approved works

* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)


approximate representation only

Daniel Rouss

Name : Daniel Rouss

Title : General Manager

Phone : (03) 8609 1844

Email : [email protected]



* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)