Wind

100 MW

Meridian Energy

-

Planned

Dargaville

NZ

-


Description:

Wind monitoring and a number of studies have been undertaken at this site since 2007. 42km transmission line is necessary to connect the wind farm to the Transpower national grid

Major Contractors/Suppliers:

-

Updates:

  • 2013 : Studies cease due to the uncertainty regarding when the wind farm might be constructed – which is dependent on electricity demand

* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)


approximate representation only

-

Name : -

Title : -

Phone : -

Email : -



* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)