Wind

332 MW

-

Goldwind Australia

-

Under Construction

Ballan

VIC

-


Description:

104 turbines with project divided into two sections, the Bungeeltap Section towards the north of the project site (50 turbines = 170 MW) and the Ballark Section to the south (54 turbines = 162 MW). Originally developed by WestWind & acquired by Goldwind in September 2016.

Major Contractors/Suppliers:

Connection: Australian Energy Operations
Network infrastructure: Beon Energy Solutions
EPC: Goldwind Australia
BOP: Zenviron

Updates:

  • 2019, Apr : First turbine installed
  • 2019, Feb : Application for generation licence submitted
  • 2018, Apr : Connection agreement signed with Australian Energy Operations
  • 2018, Jan : Construction & operation tender process started
  • 2017, Oct : Environmental plan submitted for 29km overhead transmission line to substation
  • 2016, Sep : Project acquired by Goldwind Australia from WestWind Energy
  • 2010 : Approved

* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)


approximate representation only

Alastair Smith

Name : Alastair Smith

Title : Project Development Manager

Phone : (03) 9912 7829

Email : alastairsmith@goldwindaustralia.com



* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)