Wind

157.5 MW

Acciona

$275mil

Under Construction

Mortlake

VIC

Battery


Description:

The project originally encompassed a significantly larger area comprising two sections (eastern and southern), however the eastern component was not approved by the Victorian Minister for Planning. The project now comprises the southern section only (the ‘Mortlake South Wind Farm’) including 35 turbines (not 50 as originally proposed) and an underground 220 kV transmission line of approximately 15km from the project to the Terang Terminal Station. An associated energy storage facility, still in the evaluation phase, will most likely have a capacity of between 4 MW and 5 MW.

Major Contractors/Suppliers:

Principal contractor: ACCIONA Energy
Turbines: Nordex
Towers: Keppel Prince Engineering

Updates:

  • 2019, Mar : Construction started
  • 2018, Sep : Announced as successful applicant to VRET auction
  • 2018, Apr : Declared "not a controlled action" by federal government

* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)


approximate representation only

Ben McInnes

Name : Ben McInnes

Title : Senior Manager - Project Development

Phone : (03) 9027 1008

Email : ben.mcinnes@acciona.com



* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)