Located 4km from the town centre, the project is due to start construction in 2018 to provide enough power for approximately 15,000 average homes. University of Queensland will take ownership of the project from original developer Terrain Solar once construction starts, and will own and operate the plant over its expected life.

Major Contractors/Suppliers:

Lead construction contractor: Lendlease
Inverters: Ingeteam

Updates:

  • 2019, Jul : Application made for generation licence
  • 2019, Apr : Construction officially started
  • 2018, Jun : Agreement reached for University of Queensland to assume ownership of project once constructed
  • 2018, Jun : Development approval granted
  • 2018, May : Public meeting held by council

* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)


approximate representation only

-

Name : -

Title : -

Phone : -

Email : -



* Please advise us of any errors or out of date information. While every effort is made to ensure the accuracy and currency of the information provided, Altenergy accepts no liability or responsibility for the contents of www.altenergy.com.au (click here for full Terms & Conditions)