RES puts forward a plan B for its Cannie proposal in Victoria
Published Date : 2026-November-26, Thursday
RES Australia has lodged a planning permit application with
the Victorian Government for a wind energy development near Lalbert and
Beauchamp in the Gannawarra Shire LGA, as the company progresses an alternative
to its original large-scale Cannie Wind Farm proposal.
The new development, known as Cannie Energy Park, will have a capacity of 390 MW from up to 54 wind turbines and a 200 MW / 800 MWh battery energy storage system, representing a substantially smaller development than the original proposal.
Located approximately 25km north-west of Kerang, the development area encompasses around 6200 hectares, with existing agricultural activities - including grazing and cropping – expected to continue alongside the project infrastructure.
RES estimates Cannie Energy Park will create approximately $380 million in local investment, more than 130 direct jobs and six permanent full-time positions over an operational life exceeding 30 years.
The original Cannie Wind Farm proposal is comprised up to 174 wind turbines with a combined generating capacity of approximately 1300 MW, together with battery storage infrastructure, across a project area of approximately 17,870 hectares.
RES confirmed that Cannie Energy Park is a separate project proposal and that only one of the two developments would proceed to construction. The Environment Effects Statement (EES) process for the original Cannie Wind Farm has been placed on hold.
A significant difference between the two proposals is their respective grid connection arrangements. While the original development proposed connecting to new transmission infrastructure associated with the Victoria to NSW Interconnector West (VNI West) project, Cannie Energy Park will connect to an existing 220kV transmission line to the north-east of the project site.
The connection involves approximately 3.5km of transmission infrastructure within an existing council road corridor, reducing the Cannie Energy Park’s reliance on future major transmission infrastructure.
The alternative development grid connection plan comes in the context of uncertainty surrounding the future of VNI West, with the Victorian Liberal and National parties – who are widely tipped to win the 28 November state election - committing to cancel the major transmission project.
The original Cannie Wind Farm was referred under the Commonwealth Environment Protection and Biodiversity Conservation (EPBC) Act in 2024 and was subsequently subject to Victorian environmental assessment requirements. Cannie Energy Park will be assessed under the state Development Facilitation Program.
Pictured is the original Cannie Wind Farm project area, with the 220kV transmission line visible in red and the proposed VNI West transmission line in dark blue at bottom right.